|
|
|
|
7/2 The old Band & Choir rooms had NO windows. We're cutting some in as these rooms are remodeled for Art facilities. Lots of natural light in this project!
|
|
7/8 HVAC equipment is delivered.
|
| |
|
|
|
|
7/9 Inside view of remodeling occuring in old Band & Choir rooms as they become Art facilities.
|
|
7/14 View to the west from second floor stairway as new parking lot work begins.
|
| |
|
|
|
|
7/15 A new parking lot is created at the west end of the building to replace the parking lot lost where the Music Center will be.
|
|
7/22 Madson Tile & Excavating working on the new parking lot. Campus drainage issues also being addressed here.
|
| |
|
|
|
|
7/23 Walls are framed up in the HVAC Control and storage area above the new addition.
|
|
7/24 The second floor hallway floor and celing tile is being replaced as part of this project, with funds from our annual Sunday Showcase silent auction event.
|
| |
|
|
|
|
7/30 The new parking lot to the southwest is curbed, graded & compacted.
|
|
8/6 Federally-required drainage pipe for stormwater run-off from the parking lot and roofs is laid.
|
| |
|
|
|
|
8/11 The remodeled art room (ie. the old band & choir rooms) take shape. Windows & ceiling grids installed.
|
|
8/12 The new SW parking lot is blacktopped.
|
| |
|
|
|
|
8/13 Exterior walkways are laid.
|
|
8/14 Finish grading of the excavation site is completed prior to final landscaping. The softball diamond is also being relocated in the background.
|
| |
|
|
|
|
8/15 The west parking lots not replaced are crack-filled and refinished.
|
|
8/19 The exterior portions of the cream-colored 1981 addition are re-painted a rust color to better tie in with the rest of the building.
|
| |
|
|
|
|
8/20 Students, faculty & alumni were on hand to unload semi-trailers of furniture and cabinetry.
|
|
8/20 Students, faculty & alumni move pieces of storage cabinetry & lockers.
|
| |
|
|
|
|
8/21 The music storage cabinets are installed. We are blessed with a tremendous library of music!
|
|
8/22 The administrative offices also received a face-lift this summer, with new paint, carpet, & counter tops.
|
| |
|
|
|
|
8/25 Ceiling grid is installed in the choir room prior to accoustic panels & lighting. Note the tall windows next to the lift.
|
|
8/27 Ceramic tile is installed in the main corridor of the new addition, for both appearance as well as lower ongoing maintenance costs.
|
| |
|
|
|
|
8/28 Instrument storage lockers are installed.
|
|
8/29 Landscaping is provided by Jerry Haupt of Lakeland Landscaping, Manitowoc.
|
| |
|
|
|
|
9/2 A view to the West of the re-painted exterior, while final drainage tile work is completed.
|
|
9-8 View of the choir room toward West windows. Accoustic panels being hung; ceiling complete; floor still waiting.
|
| |
|
|
|
|
9-10 View to SW from roof of new addition. Parking lot complete and lawn seeded, but storm sewer laterals from 1966 failed and require excavation & replacement.
|
|
9-18 Remodeled art room (ie. old music rooms) cabinetry & countertops near completion.
|
| |
|
|
|
|
9-23 Fire Doors are hung.
|
|
9-30 Kaeden Services of Manitowoc is finally able to install VCT tile in band & choir room after moisture is finally dealt with.
|
| |
|
|
|
|
10-1 Bathrooms near completion
|
|
10-2 View of choir room with floor tile laid and accoustic panels hung.
|
| |
|
|
|
|
10-6 Furniture in offices and practice rooms is assembled.
|
|
10-6 Music lockers and ceramic flooring in main corridor complete; lots of moving of furniture & equipment begins.
|
| |